Indonesia's nuclear regulator clears first licensing step for a planned 250MW nuclear plant in West Bangka

BAPETEN has approved PLN Nusantara Power's plan to evaluate a coastal site near Mentok for a small modular reactor, but stressed the approval is not a permit to build.

LSN Indonesia · 26 November 2026

Indonesia's nuclear regulator clears first licensing step for a planned 250MW nuclear plant in West Bangka

<p>Indonesia&#x27;s Nuclear Energy Regulatory Agency (BAPETEN) has issued a site evaluation approval for a planned nuclear power plant at Teluk Menggris in Menjelang village, Mentok district, West Bangka, in Bangka Belitung province, the agency said in a statement on Thursday (26 November), as reported by CNBC Indonesia and the energy news site Dunia Energi.</p>

<p>The approval was granted to PT PLN Nusantara Power, a subsidiary of state electricity company PLN, which plans to use an advanced small modular reactor (SMR) with a capacity of 250 megawatts and a light-water cooling system, according to the reports. BAPETEN said it reviewed the company&#x27;s site evaluation programme and site evaluation management system, submitted on 8 July 2026, and carried out field verification before issuing the approval. Agency officials and PLN Nusantara Power visited the candidate site in October, according to BAPETEN.</p>

<p>BAPETEN&#x27;s director of nuclear installation and materials licensing said the technical evaluation was completed in four months and 18 working days, faster than the six-month service standard, while maintaining a rigorous assessment. He said this showed the agency&#x27;s commitment to supporting faster licensing of nuclear reactor construction in a safe, effective and efficient way.</p>

<p>The agency stressed that the approval is not a permit to begin physical construction. A BAPETEN public relations official said it is a mandatory first step that allows the applicant to carry out more detailed investigations at the site. The site will be assessed on six aspects: seismic activity, geotechnical and foundation conditions, volcanic hazards, hydrology and meteorology, human-induced events, and the dispersion of radioactive material.</p>

<p>Under Indonesian regulations, nuclear plants of 10 to 300 megawatts must pass a staged licensing process. After site evaluation approval come site approval, design approval, a construction permit, commissioning approval and an operating licence, Dunia Energi reported.</p>

<p>Nuclear power is included in PLN&#x27;s 2025-2034 electricity supply business plan (RUPTL), approved by the Energy and Mineral Resources Ministry. The ministry has said nuclear projects in the plan are to be built in Sumatra and Kalimantan, each with a capacity of 250 megawatts, CNBC Indonesia reported.</p>

<p>File photo: Muntok harbour, West Bangka, seen from the Tanjung Kalian lighthouse. Photo: Cun Cun, CC BY-SA 4.0, via Wikimedia Commons.</p>