Long Thanh airport developer ACV asks to extend phase one deadline to 2027-2028 as key terminals slip to mid-2027
The state airports corporation told Vietnam's Standing Deputy Prime Minister that the passenger terminal, a cargo terminal and other key packages will not be finished or fully tested until June 2027, missing the National Assembly's 2026 deadline.
LSN Vietnam ·

<p>Airports Corporation of Vietnam (ACV), the developer of Long Thanh International Airport, has proposed extending the deadline for the project's first phase to 2027-2028. It told the government it cannot finish the airport's core facilities this year.</p>
<p>ACV made the request at a meeting chaired by Standing Deputy Prime Minister Pham Gia Tuc on 25 November, VnExpress and VietNamNet reported, the latter citing the government's online portal.</p>
<p>ACV said work on component project 3, which covers the essential facilities inside the airport, had reached 76.95 trillion dong, or 88.63% of contract value. Disbursement stood at 49.51 trillion dong, or 57%. Several key packages are now expected to be completed or finish trial runs only in June 2027. These include the passenger terminal, cargo terminal No. 1, the car park and the airport management system.</p>
<p>ACV described three main groups of problems. Some materials and equipment differ in manufacturer, brand, type or origin from what the contracts specified, and were ordered and installed before the investor approved the changes. Some items built and accepted under approved construction drawings do not match the approved technical design. Some items were built before their construction drawings were approved. ACV said these problems must be resolved before the works can be accepted as complete and the airport can be licensed to operate.</p>
<p>ACV asked the government to have the Ministry of Construction review the schedules of all component projects and report to the competent authorities on extending phase one to 2027-2028.</p>
<p>Concluding the meeting, Tuc called for the problems to be fixed thoroughly on the principle of not legitimising violations and not allowing new ones. He made ACV fully responsible for the schedule and quality of component project 3. He also asked the Ministry of Public Security to speed up its investigation and handling of violations linked to the project, and the Ministry of Finance to guide ACV on payment and pricing issues for imported equipment.</p>
<p>Because the project cannot be completed in 2026 as approved by the National Assembly, ACV must report to the government and the Ministry of Construction within a week of 25 November. The ministry must then report to the government by 10 December, so the competent authorities can consider adjusting the project's investment policy. Tuc said the airport may only begin operating when it meets all conditions and is safe. He told ACV to set out when the opening can be announced and to inform airlines once the authorities give notice.</p>
<p>The opening date has shifted several times. In July the Civil Aviation Authority of Vietnam said the airport was expected to start official operations on 1 December 2026. ACV later set 24 December as the start of operations and repeated that plan on 23 November.</p>
<p>Long Thanh, in Dong Nai province east of Ho Chi Minh City, covers about 5,000 hectares and has a total investment of nearly $16 billion over three phases. Phase one includes two runways and a passenger terminal designed for 25 million passengers and 1.2 million tonnes of cargo a year.</p>