Long Thanh airport's 24 December opening at risk as four packages lag and foreign airlines ask for more time

Vietnam's construction ministry warned the opening date must be weighed against real progress, while 34 international carriers want to move from Tan Son Nhat no earlier than the winter 2027 schedule.

LSN Vietnam · 20 November 2026

Long Thanh airport's 24 December opening at risk as four packages lag and foreign airlines ask for more time

<p>The planned 24 December opening of Long Thanh International Airport, Vietnam&#x27;s largest airport project, could slip because four construction packages are behind schedule, the Ministry of Construction has told government leaders, according to VnExpress and VietnamPlus.</p>

<p>The Airports Corporation of Vietnam (ACV), which runs the project in Dong Nai, wants commercial operations to begin at midnight on 24 December. In its report, the ministry said opening early would start returning the investment, but that the date must be judged against actual completion, trial results and safety checks, and that safety and security should not be traded away to hit a deadline.</p>

<p>Three of the project&#x27;s four components, covering state agency offices, air traffic management and ground services, were on track for December as of late October. The problem is component 3, the essential works: of its 16 packages, four are finished and 12 are still under way. The ministry flagged four at risk of delay: internal roads and technical infrastructure (4.8), the passenger terminal (5.10), cargo terminal 1 (7.8) and the car park building (11.5). They have been slowed by shortages of building materials and by late payments to contractors.</p>

<p>The ministry also warned that the trial-operation window is short. Integrated testing at Long Thanh is set to run for about three months, from late September to December, while large new airports usually need six to 12 months, citing International Air Transport Association practice. A short window leaves less room to fix faults that only show up when systems run together with real passengers, baggage and aircraft.</p>

<p>Airlines are also cautious. A Civil Aviation Authority of Vietnam survey found international carriers support the move from Ho Chi Minh City&#x27;s Tan Son Nhat airport, but 34 of them plan to switch from the winter 2027 schedule, and 10 of those not until summer 2028 or later. Vietnam Airlines and Vietjet are set to be the first operators. In its first phase to late March 2027, ACV plans up to 366 flights a week, 322 domestic and 44 international.</p>

<p>Permanent Deputy Prime Minister Pham Gia Tuc has told the construction ministry to have ACV draw up a safe and feasible opening plan, ordered the finance ministry to help clear payment problems, and told Dong Nai and Ho Chi Minh City to prioritise materials and fuel for the airport and speed up road links. Phase 1 of Long Thanh is designed for 25 million passengers and 1.2 million tonnes of cargo a year.</p>