Business · Malaysia Bureau
TM picked to build RM2.7 billion undersea cable linking Peninsular Malaysia with Sabah and Sarawak
The communications regulator says the roughly 5,500km SALAM system will add capacity and a backup data route between the peninsula and Borneo, with work due to start in mid-December.
LSN Malaysia ·

<p>The Malaysian Communications and Multimedia Commission (MCMC) has appointed TM Technology Services Sdn Bhd, a unit of Telekom Malaysia Bhd (TM), to design, build and operate a RM2.7 billion submarine cable system connecting Peninsular Malaysia, Sabah and Sarawak, the regulator said in a statement on Tuesday (17 November).</p>
<p>The project, called the Madani Submarine Cable Connection System (SALAM), will be funded through the Universal Service Provision (USP) Fund, MCMC said, according to Bernama as carried by Malay Mail.</p>
<p>According to MCMC, the system will run for about 5,500 kilometres and use cable technology from Alcatel Submarine Networks (ASN). The regulator said the capacity of the existing submarine cable network, in operation since 2017, is now about 85 per cent utilised.</p>
<p>SALAM will include 10 new cable landing stations: Cherating and Sedili in Peninsular Malaysia; Kuching, Sibu (Matu) and Bintulu (Samalaju) in Sarawak; and Kota Kinabalu, Kudat, Pulau Banggi, Sandakan and Tawau in Sabah, MCMC said.</p>
<p>The regulator said the extra capacity is meant to support broadband and 5G expansion, cloud services, artificial intelligence and data centres, particularly in Sabah and Sarawak, and to provide an alternative route for data traffic if existing cables are disrupted or damaged. It added that four pairs of optical fibre will be reserved for national strategic needs, including sovereign cloud infrastructure, government digital services and cybersecurity.</p>
<p>In a filing with Bursa Malaysia, TM said MCMC had approved the universal service plan and designated TM Tech as the universal service provider for the project, which it referred to as Sambungan Kabel Dasar Laut Madani Part 1, at a cost of up to RM2.7 billion, the New Straits Times reported. TM said work is scheduled to begin on 15 December 2026 and be completed in phases by the first quarter of 2030.</p>
<p>The company said it is reviewing the terms and conditions of the notification within the acceptance period, and that the project remains subject to its internal review and approval process and to the fulfilment of applicable conditions, according to the NST.</p>
<p>Earlier on Tuesday, Prime Minister Anwar Ibrahim and French President Emmanuel Macron witnessed the exchange of a memorandum of understanding between TM and ASN at the Sultan Abdul Samad Building in Kuala Lumpur, Bernama reported.</p>