Vietnam pushes North-South high-speed rail groundbreaking back to late 2028 as To Lam demands technology transfer
The project board's new schedule for the $67bn, 1,541km line comes two years after the government's earlier late-2026 target, while the Party chief and state president said Vietnam should accept only partners that transfer technology.
LSN Vietnam ·

<p>Construction of Vietnam's North-South high-speed railway is now expected to begin in late 2028, two years later than the government's earlier goal of breaking ground at the end of 2026, according to the project's management board.</p>
<p>Nguyen Trung Son, deputy director of the Thang Long Project Management Board under the Ministry of Construction, said the late-2028 target depends on the newly selected consultants meeting a 30-month timetable for the project's feasibility study, VnExpress and Thanh Nien reported on 25 November. Thanh Nien said the earlier target slipped because selecting the consultancy contractor took longer than planned.</p>
<p>On 20 November the board approved a Vietnamese-French-South Korean consortium led by France's SYSTRA for package TV-02, which covers surveys, the feasibility study, front-end engineering design and tender documents. The bid was worth more than 10.2 trillion dong (about $400 million), and the contract is expected to be signed by the end of November.</p>
<p>Under the schedule, the consultants must propose technical standards and basic design requirements within three months. By the 13th month they must submit an interim report recommending the route alignment, key control points and technology options. The feasibility study is due before an appraisal council and the Ministry of Construction by the 27th month, with final approval expected by the 30th month.</p>
<p>Topographical and geological surveys along the route are planned from the first to the third quarter of 2027. Land clearance boundaries will be handed to local authorities early so that compensation, support and resettlement can begin in 2027.</p>
<p>The same morning, To Lam, General Secretary of the Communist Party and State President, told voters in central Hanoi that Vietnam should accept only partners that meet its technical standards and transfer high-speed rail technology, VnExpress reported. He said Vietnam must first set its own railway standards before calculating investment costs, and decide which technologies, from locomotives and carriages to track, signalling and train control, must be transferred and mastered locally.</p>
<p>He warned that simply buying and assembling foreign equipment, then sending it abroad for repairs, would leave Vietnam dependent on partners and exposed to rising maintenance costs. He also asked Hanoi to prepare land for the project, tell residents about planned land acquisition, and link future stations with the city's urban transport network.</p>
<p>The National Assembly approved the investment policy for the railway in 2024. The double-track, standard-gauge line will run 1,541 kilometres from Ngoc Hoi station in Hanoi to Thu Thiem station in Ho Chi Minh City through 15 provinces and cities, with a design speed of 350 km/h, 23 passenger stations and five freight stations. Its preliminary cost is put at $67.34 billion, and it is expected to be largely complete by 2035.</p>